Exhibit 13 / 24 month rollout, two parallel tracks
Airside infrastructure and commercial validation run side by side for 24 months.
Track
Months 1 to 6
Months 7 to 12
Months 13 to 18
Months 19 to 24
MilestoneWhere the project stands
Title, JV and approvals filing
Engineering and clearances
Heavy civil works
Handover
AirsideAerospace anchor
IRB access agreement signed as a condition of the lease
Taxiway engineering layout; CRZ and environmental clearances
Grading, 11 MVA power grid, water and drainage
Phase 1 serviced plots handed to MRO and FTO operators
CommercialLifestyle validation
Hotel operator and anchor tenant letters of intent
Hospitality plot design; MahaRERA for any residential sale
Hospitality land preparation; show plots for operators
Hotel operator starts construction on its plot
CapitalMoney in
Promoter seed equity only
PE or strategic JV closes; lender appraisal
Debt drawn against clearances
First plot premiums and ground rent
Implication
Commercial plots validate demand and bring early cash while the slower airside approvals run. Neither track waits for the other.